The Wave, Bristol

Internal and external insulation. Heating pipework and ventilation ductwork systems.

Sector Leisure
Project Timeline June 19 – October 19
Value £30,000
Location Bristol
Completion Date October 19

Project Description

The Wave sits next to the 180m-long surfing lake, delivering an unrivalled inland surf experience using Wavegarden cove technology. The Wave presents an exciting opportunity both locally and globally; increased attraction to the area coupled with potential training of elite surfers amplifying competitive standing across the world.

Work Carried Out

  • Thermal Insulation to internal, external and plant area.
  • Heating pipework and ventilation ductwork systems
  • Stucco embossed aluminium sheet metal finish to plant and external pipework
  • Ductwork services with purpose made mattress jackets to pipework valves