Hilton Terminal 5, Heathrow.

New build at Terminal 5 – Heathrow Airport with a tight deadline.

Hilton Heathrow Side Image

Sector: Leisure
Location: Heathrow Airport, London

Project Timeline: 18 Months
Completed: February 2012

Value: £230,000

Project Description:

At the time of the build, this was Poplar’s largest-valued project to date. The hotel was to provide leisure facilities including swimming pool, gym and various spa facilities as well as meeting rooms and function rooms. Works were carried out to insulate all hot & cold water pipework, heating, chilled and ventilation services.

 

Work Completed:

  • Thermal Insulation and Trace Heating
  • Domestic Hot and Cold Pipework
  • Heating and Chilled Pipework
  • Ventilation Supply and Return Duct Work