Royal Naval Air Service2017-08-04T10:31:45+00:00

Royal Naval Air Service, Yeovilton.

A phased project to remove all old boilers, plant equipment and air handling units (AHU).

Sector: Industrial
Location: Yeovil

Project Timeline: 18 Months
Completed: March 2016

Value: £60,000

Project Description:

A phased project to remove all old boilers, plant equipment and air handling units (AHU). We were required to gain a military pass to site, complete thorough background checks, and prove the competency, safety and security of our team.

Once all the new services were installed, Poplar were instructed to return to site and carry out all the thermal insulation works.

 

Work Completed:

  • Thermal Insulation and Trace Heating
  • Domestic Hot and Cold Pipework
  • Heating Pipework
  • Ventilation Supply and Return Duct Work
  • Plantroom Services
  • Removals of Existing Redundant Boilers, Associated Pipework, Ventilation Ductwork and Fixings